CONSTRUCTION TIMELINE

Below are past and future milestones of the BDFP project. This will be updated accordingly should anything changes. 

2019
2020
2021
2022
2023
2024
2025
2026

DESIGN Q1 2019 TO Q1 2021

BUYOUT Q1 2020 TO Q1 2023

BIM COORDINATION Q3 2020 TO Q1 2023

SUBMITTALS & PROCUREMENT Q1 2021 TO Q4 2024

SCOPE 1: Demo Q4 2019 TO Q3 2020

SCOPE 1: Utility Relocation Q3 2020 TO Q4 2020

SCOPE 1: Site Preparation Q3 2020

SCOPE 2: Deep Foundations, Shoring, and Excavation Q4 2020 - Q3 2024

SCOPE 2: MEP & Interiors Q3 2022 - Q1 2025

COMPONENT TESTING Q3 2024 - Q3 2025

SEEDING & DIGESTER RAMP UP Q1 2025 - Q3 2025

START UP & COMMISSIONING Q1 2025 - Q1 2026

FINAL COMPLETION Q3 2026

2019
2020
2021
2022
2023
2024
2025
2026
BDFP%20Renderings_Sep%202020-1_edited.jp

CONSTRUCTION TIMELINE

Below are past and future milestones of the BDFP project. This will be updated accordingly should anything changes. 

SCOPE 1

Construction NTP

8/26/2019

SCOPE 2

RFP start

Q4 2020

SCOPE 1

Final completion

Q1 2021

SCOPE 2

Process mechanical start

Q1 2023

SCOPE 2

Prestartup testing

Q1 2024

SCOPE 2

Substantial Completion

Q1 2026

2017
2018
2019
2020
2021
2022
2023
2024
2025
2026

Project awarded

May 2017

SCOPE 2

Construction NTP

Q3 2020

SCOPE 2

Structural concrete start

Q3 2021

SCOPE 2

Start energizing building

Q3 2024

SCOPE 2

Seeding start

Q2 2025

SCOPE 2

Closeout

Q1-Q3 2026

Final completion

Q3 2026

DESIGN

Q1 2019 TO Q1 2021